Construction


Entire agreement clause - Wire

7 July 2010

Newsletters

In June, Sky was awarded damages of £318m following a long running dispute with HP Enterprise Services (formerly Electronic Data Systems Limited (EDSL)) and its American parent, Electronic Data Systems LLC (formerly Electronic Data Systems Corporation (EDSC)).

Related practice groups: Construction

Author(s): Catrin Rees



Contractual interest rates - Wire

3 July 2010

Newsletters

Since the late 1990s the Late Payment of Commercial Debts (Interest) Act 1998 (later amended and widened in 2002) (Act) allowed any party who had not been paid in the time to also be paid interest on the money not paid. A statutory rate of interest was to be paid unless the contract itself also provided for a “substantial remedy”.

Related practice groups: Construction

Author(s): Barry GoodallSally Haslewood



Condition precedents - Wire

1 July 2010

Newsletters

This case is a cautionary tale for contractors who enter into contracts that require a strict formal process in order to obtain time and money.

Related practice groups: Construction

Author(s): Jonathan Pawlowski



Carbon Reduction Commitment Energy Scheme - Wire

3 June 2010

Newsletters

In April 2010, the Carbon Reduction Commitment Energy Efficiency Scheme (CRC) came into force. The CRC is a statutory scheme that all those involved in the Construction and Property industry should be aware of, not least as it is a part of the government's target to cut emissions by 80% by 2050. To put the CRC into context, the Carbon Trust has recently stated that buildings and construction methods cause some of the worst pollution and that targets should be set to reduce emissions.

Related practice groups: Construction

Author(s): Mark Roach



Lord Justice Jackson's final report - Construction Wire

15 February 2010

Newsletters

Lord Justice Jackson's final report following his review of civil litigation costs was published on 14 January 2010. The review was held to address the high costs of civil litigation which, in the case of large complex construction disputes is often viewed by clients as being too expensive, taking too long and holding significant financial risks. These concerns have led to increasing demands by clients to seek alternative means of funding claims, fee structures and risk sharing agreements with their lawyers.

Related practice groups: Construction

Author(s): Christopher Denchfield



ODA - Health & Safety Regulations - Construction Wire

15 February 2010

Newsletters

The construction works for the 2012 Olympic Games are currently underway. Contractors, designers and CDM Co-ordinators should expect stringent health and safety requirements on any projects commissioned by the ODA. The Olympic Development Authority (ODA) has taken full responsibility for setting key performance indicators (KPIs) in its health and safety and environment standard, which will be mandatory for all projects commissions by the ODA. As a result, Contractors should expect to comply, not just with existing Health and Safety law, but any additional requirements set by the ODA.

Related practice groups: Construction

Author(s): John Malins